Structure Complete Tower-B & C Railing & Plumbing Work Completed . 85% Finishing Work complete like tile, Door & window etc
Tower-D Structure complete. Door frame fixing & Balcony Railing fixing work in progress.Plumbing work in progress
Tower-F Terrace floor pour-1 & 2 Work in progress
Commercial First floor & Second floor Work in progress.
STP slab 100 % Slab casting Complete
Boundary wall work in progress back side
Tower-G Eight floor Steel binding & shuttering WIP
Tower-A 4 th floor Steel binding & Slab Shuttering Work in progress
TOWER- B1-(G+9)-,5th-FLOOR-Steel-binding-Work-IN-PROGRESS
TOWER-A1-(G+24)-,Structure-Complete
TOWER - A2 (G+24), Ground Floor Slab (50% cast) balance slab work in progress. Mivan Mockup also work in progress pour-1
TOWER - B2(G+9),Ground floor roof slab casting complete
COMMERCIAL, Second floor Slab (50% cast) balance 50 % Steel Binding Work IN PROGRESS
A3 (G+24) Stilt Floor Slab casting complete Ground floor column & Shear wall Shuttering & casting Work in PROGRESS
TOWER-C (G+9), UGT slab casting & Plinth beam casting complete above work in progress
TOWER - A1 (G+14), COMPLETED
TOWER - A2 (G+14), COMPLETED
TOWER - A3&A4 (G+14), GROUND FLOOR IN PROGRESS
TOWER - B2 (G+6), 6TH FLOOR LEVEL IN PROGRESS
COMMERCIAL (G+1) 60% COMPLETED & IN PROGRESS
STP WALLS CASTING IN PROGRESS
TOWER-B1 (G+14), 9TH FLOOR LEVEL IN PROGRESS
UGT SLAB COMPLETED
A1&A2 BAK SIDE
BW WORK IN PROGRESS